TataCliq CPA IN

Kaj Nanavada power project

Kaj Nanavada power station is a proposed 1320 MW coal-fired power plant promoted by Mumbai based infrastructure development company named Shapoorji Pallonji Energy (Gujarat) Pvt. Ltd at Junagarh district in Gujarat, India.

In February 2011, a final draft Environmental Impact Assessment (EIA) was issued for the Kaj/Nanavada power station. Terms of Reference (TOR) for the proposed power plant were approved by India’s Ministry of Environment and Forests in May 2010.

Flipkart IN

According to a 2014 investment report on the company, the total project cost for “Phase I has witnessed cost overruns and is currently estimated at about Rs. 7,700 crore.” The power station is planned for commissioning in May 2015.

Coal Linkage

Indonesian coal of GCV 5000 kcal/kg (approximate) will be imported for the proposed power project. The estimated imported coal requirement is approx. 4.5 Million Ton per Annum (considering 90% PLF). Coal supply agreement for sourcing Inodonesian coal has been executed. This Imported coal will be transported from the proposed port at Charra to proposed power plant site through twin stream pipe conveyor.

Land Requirement

Approximately 340 ha of land have been identified for the power station including ash pond, coal stockpile, green belt etc. Additional land area of approx. 25ha has been identified for coal/water corridor.

Water

The consumptive water requirement for the 2 x 660 MW plant is about 13,193 m3/hr for cooling, process use and other miscellaneous uses. Sea water will be used which will be supplied from the intake pump house proposed to be located at a distance of about 7 km from the project site.

Project Details

8 thoughts on “Kaj Nanavada power project

  • January 21, 2017 at 12:45 pm
    Permalink

    Hello sir I’m Pratikkumar solanki from diu I have completed be mechanical in 2016 and 7th month experience. Abc bearings Ltd BHARUCH so I want job in your company.my contact number is 8690105436

  • April 3, 2017 at 10:02 pm
    Permalink

    Hello sir
    I have completed my iti electrician in two years than 4.7years experience
    1: currently working at adani solar technopark mundra under contract thermax limited.
    2: worked in reliance industries ltd under contract t.s engineering.
    3: worked in ford moto company at sanand.
    4: worked in Gujarat sidhee cement limited.

  • July 1, 2017 at 10:22 pm
    Permalink

    Hello sir l have complete my iti electrician in two years experience v
    1.bkt tayer bhuj 2.zydus cedila Ahmedabad 3. Matharshad sumi system l.t.d. my contact number is 7227083287

  • April 3, 2018 at 8:14 pm
    Permalink

    Hello sir , this is Vikas Goswami From – Mumbai

    i have complete my Computer Hardware in IT and currently working with Bonanza Portfolio Ltd.
    Mumbai as a IT BackOffice Engineer sins 2013 ,
    now i am find job near kodinar i wood like to job in your company so please contact me @ 9029407027 or mail @ goswamivikas.p@gmail.com if any IT related Opening are there in Shapoorji Pallonji Energy (Kodinar-Gujarat) Pvt. Ltd

    Thank you

  • May 18, 2018 at 10:39 am
    Permalink

    Hello sir
    I have completed my Diploma electrical in 3 years than 4.5years experience
    1: currently working at Sterlite Power Transmission Limited.
    2: worked in Suzlon global service limited.
    3: worked in Gujarat Sidhee cement Limited.
    4: worked in Ambuja cement limited.

Leave a Reply