Salora power project

Salora power project is proposed 1890 MW coal fired power plant promoted by Vandana Vidhyut at Korba district in Chhattisgarh, India

Unit Specification

Unit 1 (135 MW) was commissioned on 10 April 2014.

Flipkart IN

Unit 2 (135 MW) is under construction and planned for March 2015.

Unit 3 (270 MW) is scheduled for September 2017.

Unit 4 (660 MW) is scheduled for September 2020.

Unit 5 (660 MW), which was previously included in future plans, is no longer mentioned on the company website.

Status of phase I (540 MW)

As of August 2014, the company lists the following milestones for the first 540 MW of power:

  • Land for 540 MW already acquired.
  • Implementation agreement signed with the Chhattisgarh Government already entered.
  • Environment Clearance obtained .
  • Water allotted 18 McM water from Hasdeo River.
  • The company has secured supply of coal by Captive Coal Mine in JV ( Fatehpur East Coal Pvt. Ltd).
  • Coal linkage with SECL
  • Long Term open access for IPP already obtained from Power Grid Corporation Limited .
  • PPA is signed with CSPTCO.
  • Power Trading Category III license has been obtained.

Project Details

  • Sponsor: Vandana Vidhyut
  • Parent company:
  • Location: Salora, Chhuri, and Dhanras villages, Katghora taluk, Korba district, Chhattisgarh
  • Coordinates: 22.4899525, 82.6062387
  • Status:
    • Unit 1: Operating (2014)
    • Unit 2: Construction
    • Unit 3: Permitted
    • Unit 4: Announced
    • Unit 5: Cancelled
  • Gross Capacity:
    • Unit 1: 135 MW
    • Unit 2: 135 MW
    • Unit 3: 270 MW
    • Unit 4: 660 MW
    • Unit 5: 660 MW
  • Type: Ultra-supercritical
  • Projected in service:
    • Unit 1: Operating 2014
    • Unit 2: 2015
    • Unit 3: 2017
    • Unit 4: 2020
  • Coal Type: Bituminous
  • Coal Source: Fatehpur East Coal Block ( Cancelled as per the ruling of  supreme  court)
  • MoEF permits (Units 1-3 only): Environmental clearance J-13011/632008-IA.II(T), March 9, 2009